If SPI > 1 and CPI > 1, what can be inferred about project performance?

Prepare for the PMT 4910 Advanced Certification Exam with our comprehensive quiz. Benefit from a variety of question formats, including flashcards and multiple-choice, with detailed explanations and tips to boost your confidence and readiness for the test.

Multiple Choice

If SPI > 1 and CPI > 1, what can be inferred about project performance?

Explanation:
SPI and CPI are earned value metrics that show how well a project is meeting its schedule and cost goals. SPI (schedule performance index) compares earned value to planned value; CPI (cost performance index) compares earned value to actual cost. If SPI > 1, more work has been completed than planned for the given time, meaning the project is ahead of schedule. If CPI > 1, the value of work done costs less than it was planned, meaning cost efficiency or under budget for the work performed. When both indices exceed 1, you have favorable results in both dimensions. So, the project is ahead of schedule and cost-efficient.

SPI and CPI are earned value metrics that show how well a project is meeting its schedule and cost goals. SPI (schedule performance index) compares earned value to planned value; CPI (cost performance index) compares earned value to actual cost. If SPI > 1, more work has been completed than planned for the given time, meaning the project is ahead of schedule. If CPI > 1, the value of work done costs less than it was planned, meaning cost efficiency or under budget for the work performed. When both indices exceed 1, you have favorable results in both dimensions. So, the project is ahead of schedule and cost-efficient.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy